Finland, in preparationSweden, in preparationEstonia, in preparationDenmark, in preparationLatvia, in preparationLithuania, in preparationBelgium, in preparationCzechia, in preparationLuxembourg, in preparationSlovakia, in preparationAustria, in preparationHungary, in preparationRomania, in preparationCroatia, in preparationPortugal, in preparationGreece, in preparationCyprus, in preparationMalta, in preparationIrelandGermanyPolandNetherlandsFranceItalySloveniaSpainBulgaria
Profile In preparation Outside the EU

Country profile

Poland

Poland's PLN 4.8bn price-relief bill for 2027 to 2030 is in parliament, and its capacity market has run since 2018.

Key figures

Industrial electricity price
168.7 €/MWh
Day-ahead price, 2025 average
105 €/MWh
Renewables share, 2025
31 %
Negative-price hours, 2025
No annual count published
Electricity demand (PSE), 2025
167.5 TWh
Network costs, 20 to 70 GWh users (Eurostat), 2025
0.028 €/kWh

Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand (PSE): PSE, Raporty za rok 2025 (Raport 2025 KSE), as published (no date on page). Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.

Policies

Price relief (CISAF 4.5)DraftThe act would fund PLN 4.8bn of price relief for 2027 to 2030. Parliament passed it on 5 Nov 2026, and it awaits the President's signature.What it means: Aid applied for in 2027 would be based on 2026 consumption, once the act is signed and the Commission approves the scheme.

Act on support for energy-intensive companies, PLN 4.8bn for 2027 to 2030. Passed by parliament on 5 Nov 2026 and with the President since 6 Nov; not yet law.

Poland's act on support for energy-intensive companies implements CISAF section 4.5. It caps support at 50% of the reference price and at a level that keeps the price paid at or above €50 per MWh. Firms must invest at least half the aid in flexibility, electrification or renewables within 48 months. State spending is capped at PLN 4.8 billion over 2027 to 2030. Aid is based on the calendar year before the application, so applications in 2027 would cover 2026 consumption. The act would take effect on 1 January 2027.

Budget ceiling 2027 to 2030
PLN 4.8 billion (800m, 1,600m, 1,600m, 800m) Act of 22 Oct 2026 as passed by the Sejm, art. 33(1), 22 Oct 2026
Maximum support
50% of the reference price; price after support not below €50/MWh Act of 22 Oct 2026 as passed by the Sejm, art. 3(4), 22 Oct 2026
Qualifying period
The calendar year before the application (2026 for applications in 2027) Act of 22 Oct 2026 as passed by the Sejm, art. 2(4), 22 Oct 2026

Source: Sejm, process 3159

Legal texts: Sejm, process 3159

CO₂ cost compensationIn forcePoland refunds part of the CO₂ cost built into power prices under the Act of 19 Jul 2019, run by URE.What it means: Applications for the previous year's costs are due by 31 March each year.

Compensation under the Act of 19 Jul 2019, run by URE. Applications are due by 31 Mar for the previous year.

Poland compensates energy-intensive companies for carbon costs passed into electricity prices under the Act of 19 July 2019. The President of URE, the energy regulator, decides on each application. Applications for a year are due by 31 March of the following year, and URE decides by 31 October. Aid intensity is 0.75 in the calculation formulas. The yearly pot equals set ETS auction revenues, cut pro rata if claims exceed it.

Application deadline
31 Mar of the following year Dz.U. 2026 poz. 807, art. 10(2), 29 May 2026
Aid intensity in formulas
0.75 Dz.U. 2026 poz. 807, art. 7, 29 May 2026

Source: Dz.U. 2026 poz. 807

Legal texts: Rekompensaty (Act of 19 Jul 2019)

Grid fee reliefIn forceRegistered industrial consumers pay reduced renewable and CHP charges.What it means: Sites must file a declaration by 15 Nov to claim the reduction.

Registered industrial consumers pay reduced renewable and CHP charges. Declarations are due by 15 Nov.

Registered industrial consumers pay the renewable (OZE) and cogeneration charges on only 15% or 25% of the electricity they draw from the grid. To qualify, a firm's main activity must fall under listed PKD codes and its electro-intensity must be at least 3%. Firms file a declaration with an auditor's opinion with URE. For rights in 2026 the deadline was 15 November 2025. Missing it removes the relief for that year.

Charge basis for registered industrial consumers
15% or 25% of electricity drawn and consumed URE, Informacja Prezesa URE nr 59/2025, 6 Nov 2025
Declaration deadline for 2026 rights
15 Nov 2025 URE, Informacja Prezesa URE nr 59/2025, 6 Nov 2025

Source: Enerad, 2025 (secondary)

Storage rulesIn forceNetwork fees on storage are charged on net energy only, including batteries inside a customer's installation with their own meter.

Network charges on energy drawn by a storage facility apply only to the difference between energy taken from and returned to the grid in each billing period. This also covers storage that is part of a final customer's installation, provided it has its own meter recording energy in and out. The contracted capacity used for billing is reduced in proportion to the share of energy the storage returns to the grid.

Source: Energy Law, art. 45 (Dz.U. 2026 poz. 43)

Legal texts: Prawo energetyczne, art. 45

Capacity mechanismIn forceCapacity market since 2018. The delivery-year 2030 auction cleared at PLN 465.02/kW-year.

Poland runs a capacity market under the Capacity Market Act of 8 December 2017, with PSE as operator. The main auction for delivery year 2030 took place on 11 December 2025 and ended in the second round at PLN 465.02 per kW-year for Polish units. It awarded 6,887.639 MW to 198 winning offers. Demand-response units and battery projects were among the winners. Including earlier multi-year contracts, obligations for 2030 total 21,785.155 MW.

Clearing price, delivery year 2030
PLN 465.02/kW-year URE, Informacja Prezesa URE nr 1/2026, 2 Jan 2026
Capacity obligations awarded in the auction
6,887.639 MW URE, Informacja Prezesa URE nr 1/2026, 2 Jan 2026

Source: URE, Informacja 1/2026

Legal texts: Rynek mocy (URE)

Next dated changeDatedWith the President since 6 Nov 2026, who has 21 days to sign or veto the act. Planned entry into force 1 Jan 2027; no aid before Commission approval under CISAF.

The Sejm passed the act on support for energy-intensive companies on 22 October 2026. The Senate adopted 13 amendments on 27 October, and the Sejm accepted them on 5 November. The act went to the President on 6 November; he has 21 days to sign or veto it. The act would take effect on 1 January 2027. Support also needs Commission approval under CISAF and a government aid programme, with applications run by the state bank BGK.

Sejm vote (third reading)
22 Oct 2026 (230 for, 64 against, 145 abstaining) Sejm API, process 3159, 22 Oct 2026
Senate position (amendments)
27 Oct 2026 Sejm API, process 3159, 27 Oct 2026
Senate amendments accepted; sent to the President
5 Nov 2026; 6 Nov 2026 Sejm API, process 3159, 6 Nov 2026
Planned entry into force
1 Jan 2027 Act of 22 Oct 2026, art. 35, 22 Oct 2026

Source: Sejm, process 3159

Updates

Results for Poland follow once its eligibility rules are mapped to sectors

Checked 31 Oct 2026. Not legal, tax or investment advice.