Finland, in preparationSweden, in preparationEstonia, in preparationDenmark, in preparationLatvia, in preparationLithuania, in preparationBelgium, in preparationCzechia, in preparationLuxembourg, in preparationSlovakia, in preparationAustria, in preparationHungary, in preparationRomania, in preparationCroatia, in preparationPortugal, in preparationGreece, in preparationCyprus, in preparationMalta, in preparationIrelandGermanyPolandNetherlandsFranceItalySloveniaSpainBulgaria
Profile In preparation Outside the EU

Country profile

Italy

Italy has the second-highest industrial power price of the nine markets and raised its CO₂ compensation budget to €3.6bn in 2026.

Key figures

Industrial electricity price
172.6 €/MWh
Day-ahead price, 2025 average
116 €/MWh
Renewables share, 2025
49 %
Negative-price hours, 2025
0 h
Electricity demand (Terna, provisional), 2025
311.3 TWh
Network costs, 20 to 70 GWh users (Eurostat), 2025
0.017 €/kWh

Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand (Terna, provisional): Terna, 'Nel 2025 fabbisogno elettrico pari a 311,3 TWh', 21 Jan 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.

Policies

Price relief (CISAF 4.5)None foundNo CISAF price-relief scheme found. Energy Release 2.0 runs outside that framework.What it means: Italian power-cost relief for industry comes through Energy Release 2.0, not a CISAF scheme.

No CISAF 4.5 scheme found. Energy Release 2.0, outside that section, advances renewable power to energy-intensive users at €65/MWh for 2025 to 2027.

We found no Italian scheme under CISAF section 4.5. Italy's main tool for energy-intensive users is Energy Release 2.0, which sits outside that section. The state energy agency GSE advances renewable electricity to energy-intensive companies for 2025 to 2027 at €65 per MWh. In return, companies must build new renewable capacity and give the energy back over 20 years. Italy amended the scheme in July 2025 to meet conditions set by the Commission in a letter of 27 June 2025.

Energy Release 2.0 transfer price
€65/MWh MASE directorial decree 104 of 17 Dec 2025, Annex 1, 17 Dec 2025
Repayment period
20 years from plant commissioning MASE directorial decree 104 of 17 Dec 2025, Annex 1, 17 Dec 2025

Source: MASE directorial decree 104, 17 Dec 2025

CO₂ cost compensationIn forceItaly raised its CO₂ cost compensation budget from €1.5bn to €3.6bn and the aid intensity to 80%.What it means: Eligible sites can recover up to 80% of their eligible indirect CO₂ costs.

Budget raised from €1.5bn to €3.6bn and aid intensity to 80% (SA.122463).

Italy compensates energy-intensive companies for the carbon cost passed into electricity prices. In July 2026 the Commission approved an amendment to the scheme (SA.122463). The total budget rises from €1.5 billion to €3.6 billion and the annual ceiling from €140 million to €600 million. Aid intensity rises from 75% to 80%, for sectors already covered. New sectors at risk of carbon leakage become eligible. Final payments are due in 2031.

Total budget (amended)
€3.6 billion (from €1.5 billion) European Commission, MEX/26/1656, 20 Jul 2026
Maximum annual budget
€600 million (from €140 million) European Commission, MEX/26/1656, 20 Jul 2026
Maximum aid intensity (existing sectors)
80% (from 75%) European Commission, MEX/26/1656, 20 Jul 2026

Source: European Commission, MEX/26/1656, 20 Jul 2026

Legal texts: Compensazione costi indiretti (SA.122463)

Grid fee reliefIn forceSince 1 Apr 2026, non-household users pay about €12 to €14/MWh less in the ASOS system charge.What it means: The system-charge line of the bill is lower. Sites on the CSEA energy-intensive list are excluded.

Since 1 Apr 2026, ARERA has applied an ASOS discount of about €12 to €14/MWh for non-household users under DL 21/2026. Users on the CSEA energy-intensive list are excluded.

Decree-law 21/2026, converted with amendments by Law 49/2026, cuts the ASOS charge, the system charge that funds renewables and cogeneration, for non-household users. ARERA has applied the cut since 1 April 2026 through a negative ASOS element worth about €12 to €14 per MWh, depending on voltage. So far it is funded by a temporary 2-point IRAP rise on energy companies, with resources estimated at €469.6 million for 2026, €545.4 million for 2027 and €74.5 million for 2028, and by bringing forward system-charge payments in 2026. Savings from Conto Energia solar owners who accepted a lower premium by 31 May 2026 are also earmarked for it. Public lighting and companies on the CSEA energy-intensive list are excluded. ARERA raised the overall ASOS charge from 1 July 2026.

IRAP resources earmarked for the ASOS cut, 2026
€469.6 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
IRAP resources earmarked for the ASOS cut, 2027
€545.4 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
IRAP resources earmarked for the ASOS cut, 2028
€74.5 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
Deadline for PV owners to opt into a reduced premium
31 May 2026 DL 21/2026, art. 2(3), Gazzetta Ufficiale n. 42, 20 Feb 2026

Source: ARERA deliberation 98/2026/R/com, 30 Mar 2026

Legal texts: DL 21/2026 (decreto bollette) · ARERA deliberation 98/2026/R/com

Storage rulesIn forceSince 2022, energy drawn to charge storage and later fed back can be netted, so grid tariffs and system charges apply only to energy consumed.

Since 1 January 2022, a producer can ask for energy drawn from the grid to charge storage, and later fed back, to be treated as negative injection. Transmission and distribution tariffs and system charges then apply only to energy actually consumed. The request needs a single-line diagram and an independent certified rating. If charging power exceeds 110% of the declared value in a month, normal consumer charges apply through a penalty.

Penalty threshold for charging power
110% of declared power in a month ARERA Delibera 109/2021/R/eel, point 2, 16 Mar 2021

Source: ARERA, Delibera 109/2021/R/eel

Legal texts: ARERA 109/2021/R/eel

Capacity mechanismIn forceTerna capacity market. The first MACSE storage auction awarded 10 GWh in Sep 2025.

Terna runs a capacity market and, separately, MACSE, a scheme that procures new storage under long-term contracts. The first MACSE auction on 30 September 2025 procured 10 GWh in southern Italy and the islands, all of the demand. Bids exceeded demand more than four times. The weighted average price was €12,959 per MWh-year, against a reserve premium of €37,000. The lithium-ion plants are due to start operating in 2028.

Storage procured, first MACSE auction
10 GWh Terna press release, 1 Oct 2025
Weighted average clearing price
€12,959/MWh-year Terna press release, 1 Oct 2025
Reserve premium
€37,000/MWh-year Terna press release, 1 Oct 2025

Source: Terna via Teleborsa, 1 Oct 2025

Legal texts: Capacity market and MACSE (Terna)

Next dated changeDated21 Dec 2026: Terna holds the main capacity market auction for 2028 delivery.

The rules for the capacity market auction with 2028 delivery were approved by ministerial decree on 6 August 2026, with technical provisions approved on 16 October 2026. Terna has scheduled the main auction for 21 December 2026 at 10:00. Requests to take part could be sent from 20 October to 3 November 2026. The 16 October decree also approved revised de-rating factors for new battery storage, which the ministry had asked Terna to review.

Source: Terna, 19 Oct 2026

Updates

Results for Italy follow once its eligibility rules are mapped to sectors