EUindustrials EN DE ES

Country profiles

Finland, in preparationSweden, in preparationEstonia, in preparationDenmark, in preparationLatvia, in preparationLithuania, in preparationBelgium, in preparationCzechia, in preparationLuxembourg, in preparationSlovakia, in preparationAustria, in preparationHungary, in preparationRomania, in preparationCroatia, in preparationPortugal, in preparationGreece, in preparationCyprus, in preparationMalta, in preparationIrelandGermanyPolandNetherlandsFranceItalySloveniaSpainBulgaria
Profile In preparation Outside the EU

Country profile

Netherlands

The Netherlands plans a €150m price-relief scheme for 2027 and a first capacity auction for 2028, but no grid fee relief.

Key figures

Industrial electricity price
139.1 €/MWh
Day-ahead price, 2025 average
88 €/MWh
Renewables share, 2025
49 %
Negative-price hours, 2025
584 h
Net electricity consumption (CBS), 2025
112.8 TWh
Network costs, 20 to 70 GWh users (Eurostat), 2025
0.022 €/kWh

Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Net electricity consumption (CBS): CBS StatLine 84575NED, Elektriciteitsbalans; aanbod en verbruik, 30 Oct 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.

Policies

Price relief (CISAF 4.5)PlannedThe Dutch cabinet intends to open a €150m CISAF price-relief scheme in 2027.What it means: Dutch sites have no power-price relief yet. The scheme still has to be designed and approved, and half of any aid must be reinvested.

The cabinet intends to open a €150m CISAF price-relief scheme in 2027 (letter to parliament, 3 Nov 2026). Not yet designed or approved.

On 3 November 2026 the cabinet told parliament that it intends to open a €150 million scheme under CISAF section 4.5 in 2027, using the extra room the temporary METSAF framework allows. CISAF requires beneficiaries to invest at least half of the aid in decarbonisation, such as energy efficiency, electrification or flexibility. The scheme is not yet designed or approved. Dutch support for industrial electricity costs currently runs through compensation for indirect carbon costs, the IKC-ETS scheme.

Source: Kamerbrief Elektriciteitskosten industrie, 3 Nov 2026

Legal texts: Kamerbrief Elektriciteitskosten industrie (3 Nov 2026)

CO₂ cost compensationIn forceIKC-ETS refunds part of the CO₂ cost built into power prices. The 2026 round had €318m for 2025 costs.What it means: The 2026 round closed on 30 Sep 2026; sites that missed it wait for the next round.

IKC-ETS. The 2026 round (2025 costs, €318m) closed on 30 Sep 2026.

The IKC-ETS scheme refunds part of the carbon cost in power prices. The 2026 round covered costs incurred in 2025, with a budget of €318.2 million. Applications ran from 3 August to 30 September 2026. Aid is 80% of indirect costs for long-listed sectors and 75% for newly added ones. Large companies need an energy audit and must invest at least half the subsidy in carbon reduction. Payment awaits Commission approval.

Budget ceiling, 2026 round (2025 costs)
€318,239,000 Staatscourant 2026, nr. 24870, 15 Jul 2026
Application window
3 Aug to 30 Sep 2026 Staatscourant 2026, nr. 24870, 15 Jul 2026
Aid intensity
80% (existing sectors); 75% (newly added sectors) Staatscourant 2026, nr. 24870, 15 Jul 2026

Source: Staatscourant 2026, nr. 24870

Legal texts: IKC-ETS (RVO)

Grid fee reliefNoneThe volume-correction rebate ended in 2024, and no grid-fee relief replaces it.What it means: TenneT proposes 2027 high-voltage tariffs 20% higher on average, with no rebate to offset the rise. ACM decides in November.

The volume-correction rebate ended in 2024. TenneT proposes 2027 high-voltage tariffs 20% higher on average and extra-high-voltage tariffs 6% lower; ACM decides in Nov 2026.

The Netherlands has no grid-fee discount for large consumers. ACM ended the volume-correction scheme, a transport-tariff rebate for users with high, steady consumption, from 2024. It found these users did not cause lower grid costs. ACM's first forecast is that large companies connected to TenneT's high-voltage grid will pay about 20% more in 2027. TenneT's proposal shows high-voltage tariffs up 20% on average and extra-high-voltage tariffs down 6%.

Expected 2027 change for large users on TenneT's high-voltage grid
about +20% ACM, first forecast of 2027 tariffs, 14 Sep 2026
TenneT proposal, average 2027 change: HS / EHS
+20% / -6% TenneT tariff proposal 2027 (published by ACM), 29 Sep 2026

Source: ACM, 7 Oct 2026

Storage rulesIn forceNon-firm grid contracts with a tariff discount, offered in congested areas since Feb 2025. No storage exemption.

In congested areas, grid operators must offer non-firm transport contracts. These give a discount on the transport tariff in exchange for using the connection only when capacity is available. Operators could offer them from 1 February 2024 and have had to since 1 February 2025. ACM names battery storage among suitable users. We found no general exemption from grid fees for stored energy in the Netherlands.

Non-firm contracts mandatory in congestion areas from
1 Feb 2025 ACM, 31 Jan 2024, 31 Jan 2024

Source: ACM, 31 Jan 2024

Legal texts: Non-firm transport contracts (ACM)

Capacity mechanismPlannedMarket-wide capacity market chosen in Jun 2026. First auction targeted for 2028, subject to state-aid approval.

On 19 June 2026 the cabinet chose a market-wide capacity mechanism to protect against shortages and price spikes. TenneT's monitoring shows the Dutch standard of at most 4 hours of expected shortage a year will be exceeded in all scenarios in 2030. TenneT would run the auctions, with the first targeted for 2028 for supply in 2029 to 2030. Batteries and demand response can take part. The timeline depends on Commission approval.

First auction targeted
2028 Rijksoverheid, 19 Jun 2026, 19 Jun 2026
Supply period targeted
2029 to 2030 Rijksoverheid, 19 Jun 2026, 19 Jun 2026

Source: Rijksoverheid, 19 Jun 2026

Legal texts: Capaciteitsmarkt (planned)

Next dated changeDatedNov 2026: ACM decides on the 2027 tariff proposals of TenneT and the regional grid operators.

ACM is assessing the grid operators' tariff proposals for 2027 and says it will decide on them in November 2026. TenneT's proposal raises average high-voltage transport tariffs by 20% and lowers extra-high-voltage tariffs by 6%. ACM's earlier forecast put the increase for large companies on TenneT's high-voltage grid at about 20%. The final tariffs will show whether ACM adopts TenneT's proposal.

Source: ACM, 7 Oct 2026

Updates

Results for Netherlands follow once its eligibility rules are mapped to sectors

Checked 31 Oct 2026. Not legal, tax or investment advice.