Country profiles
Country profiles
Support schemes, grid fees, storage rules and market figures for nine EU markets.
| Market | Price relief (CISAF 4.5) | CO₂ cost compensation | Grid fee relief | Storage rules | Capacity mechanism |
|---|---|---|---|---|---|
| Bulgaria | In force | None | None | In force | None |
| Germany | In force | In force | Ending | In force | In force |
| Spain | None | In force | 2026 only | In force | Adopted |
| France | None found | In force | In force | In force | In force |
| Ireland | In force | None | None | In force | In force |
| Italy | None found | In force | In force | In force | In force |
| Netherlands | Planned | In force | None | In force | Planned |
| Poland | Draft | In force | In force | In force | In force |
| Slovenia | In force | In force | In force | In force | None |
Status as of 31 Oct 2026; Bulgaria, Ireland and Slovenia as of 11 Nov 2026.
Country profile
Bulgaria
Bulgaria cuts energy-intensive sites' power bills monthly under a €334m scheme until June 2028, but pays no CO₂ compensation.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Gross electricity consumption (ESO): ESO, Статистическа книжка 2025 (Statistical pocketbook 2025), 30 Mar 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)In forceBulgaria's CISAF scheme cuts the power bills of energy-intensive sites every month until June 2028, with €334m of funding.What it means: An eligible site applies through its supplier and gets relief on half of its eligible consumption, but must reinvest half of the aid.
CISAF scheme SA.120414, €334m for 1 Jul 2025 to 30 Jun 2028, paid as a monthly cut in the supplier's invoice. Half of the aid must be reinvested.
Bulgaria's scheme implements CISAF section 4.5 and was approved by the Commission on 16 April 2026 as SA.120414. It covers non-household customers that carried out an activity in one of 91 sectors listed in Annex 1 to the 2022 climate, energy and environment aid guidelines in the previous year; since June 2026 a firm with several activities claims for its eligible share. Each month the supplier cuts the invoice by up to 50% of the IBEX day-ahead baseload average on half of the eligible consumption, without taking the firm's own price below a floor. The floor is €63.91/MWh, lowered to €50/MWh for July 2026 to June 2027. Firms apply to their supplier for each price period, the Electricity System Security Fund repays suppliers, and the Ministry of Energy administers the scheme. At least half of the aid must go into renewables, storage, demand flexibility, efficiency, electrolysers or electrification operating within 48 months, or the aid is repaid with interest. Customers outside the scheme fall under a general programme that compensates part of prices above €122.71/MWh, and a site can use only one of the two.
- Total budget, 1 Jul 2025 to 30 Jun 2028
- €334m Decree No 68 of 11 Jun 2026, § 2 (State Gazette No 55), 11 Jun 2026
- Budget, first price period (Jul 2025 to Jun 2026)
- up to €124m Decree No 68 of 11 Jun 2026, § 2 (State Gazette No 55), 11 Jun 2026
- Budget, second price period (Jul 2026 to Jun 2027)
- up to €170m Council of Ministers Decision No 706, 9 Sep 2026
- Floor on the firm's price after aid
- €63.91/MWh; €50/MWh for Jul 2026 to Jun 2027 Council of Ministers Decision No 706, 9 Sep 2026
- Maximum aid
- 50% of the IBEX day-ahead baseload average, on 50% of consumption for eligible activities Decree No 68 of 11 Jun 2026, §§ 6 and 7 (arts 12 and 13), 11 Jun 2026
- Final payments due by
- 30 Jun 2029 Decree No 237/2025, art. 3, 11 Nov 2025
Source: Decree No 237/2025 (State Gazette No 96, 11 Nov 2025)
Legal texts: ПМС № 237/2025 (ДВ, бр. 96/2025) · ПМС № 68/2026 (ДВ, бр. 55/2026) · РМС № 706/2026 (budget and floor, 2026-27) · РМС № 730/2026 (general compensation) · European Commission, SA.120414 decision
CO₂ cost compensationNoneBulgaria has no scheme refunding the CO₂ cost built into power prices, and told the Commission it plans none.What it means: Bulgarian sites cannot recover the CO₂ cost in their power bills.
No compensation for indirect CO₂ costs. The Commission's April 2026 decision records that Bulgaria has no plans for a scheme.
Bulgaria has no scheme that compensates energy-intensive firms for the carbon cost passed into electricity prices under the 2021 ETS state-aid guidelines. In its decision approving the CISAF scheme on 16 April 2026, the Commission records that Bulgaria has no plans to introduce one. The CISAF decree only caps combined aid should such a scheme be created.
Source: European Commission decision C(2026) 2565, recital 39
Legal texts: European Commission, decision C(2026) 2565 (SA.120414)
Grid fee reliefNoneBulgaria has no grid-fee relief for large consumers. The obligations-to-society levy is €0/MWh for all consumers from 1 Jul 2026.What it means: Large sites pay standard network tariffs and, in the current price period, no levy for renewable and CHP support.
No network-charge relief for large or energy-intensive users. The obligations-to-society levy is €0/MWh for all consumers from 1 Jul 2026.
Bulgaria has no network-charge discount for large, steady or energy-intensive consumers, and EWRC applies the same access and transmission prices to all non-household customers. From 1 July 2026 end customers pay €0.18/MWh for access to the transmission grid and €8.01/MWh for transmission. Customers on a distribution grid also pay a capacity-based access price and a medium-voltage transmission price of €7.94 to €9.24/MWh, depending on the operator. The obligations-to-society price, which funds renewable and CHP support through the Electricity System Security Fund, is €0/MWh because the fund's revenues cover those costs; it was also zero in 2025-26. A scheme that cut this levy for energy-intensive firms ran until 31 December 2021.
- Obligations-to-society price from 1 Jul 2026
- €0.00/MWh EWRC decision Ц-13/01.07.2026, point I.6, 1 Jul 2026
- Transmission access and transmission prices for end customers from 1 Jul 2026
- €0.18/MWh + €8.01/MWh EWRC decision Ц-13/01.07.2026, points I.1.1 and I.1.4, 1 Jul 2026
- Medium-voltage distribution transmission price from 1 Jul 2026
- €7.94 to €9.24/MWh, by operator EWRC decision Ц-13/01.07.2026, points I.2 to I.4, 1 Jul 2026
- Obligations-to-society price from 1 Jul 2025
- BGN 0.00/MWh EWRC decision Ц-25/01.07.2025, 1 Jul 2025
- Energy-intensive relief from the renewables levy
- ended 31 Dec 2021 Ordinance amending Ordinance No Е-РД-04-06/2016, § 1 (State Gazette No 12/2021), 12 Feb 2021
Source: EWRC decision Ц-13, 1 Jul 2026
Legal texts: КЕВР, Решение № Ц-13/01.07.2026
Storage rulesIn forceBatteries pay network charges and the obligations-to-society levy only on energy bought minus energy fed back. Storage may sit at a new or existing consumption site.
The Energy Act lets a storage facility be built at a new or existing production or consumption site, or as a stand-alone plant (art. 90a). Its operator pays network charges and the obligations-to-society price only on the energy bought minus the energy fed back to the grid (art. 90b(3)). EWRC states that storage without its own connection or separate metering, inside a consumption site, pays no separate access or transmission prices; its costs fall within the site's own network charges. A battery serving only the site's own consumption, which never feeds the grid, is outside the legal definition of a storage facility. The Act defines the operator as any natural or legal person responsible for running the facility, and a licence is needed only for stand-alone storage whose operator trades electricity. Installed battery capacity reached 4,011 MW and 12,240 MWh by early June 2026.
- Basis for network charges and the levy on storage
- energy bought minus energy fed back Energy Act, art. 90b(3) (State Gazette No 11/2023), 2 Feb 2023
- Installed battery storage, early June 2026
- 4,011 MW / 12,240 MWh (3,471 MW on the transmission grid) EWRC report on storage and industrial consumers in the balancing market, 21 Aug 2026
Source: Energy Act, arts 90a and 90b (State Gazette No 11/2023)
Legal texts: Закон за енергетиката, чл. 90а и 90б · КЕВР, доклад за BESS и DSR на балансиращия пазар (21.08.2026)
Capacity mechanismNoneNo capacity mechanism. ESO buys frequency reserves in tenders open to batteries and industrial loads from 1 MW.
Bulgaria has no capacity mechanism. ACER's 2025 monitoring report lists investment support for battery storage as Bulgaria's only security-of-supply measure in 2024 and shows no capacity mechanism in 2025. The Energy Act's cold-reserve provisions, which paid power plants to stand by, were removed in February 2021. ESO buys frequency containment and restoration reserves in tenders open to batteries and industrial consumers from 1 MW, alone or through an aggregator, and since May 2024 it may also contract reserves from storage not yet built. At the end of 2025, 22 providers were registered; the one industrial consumer among them was inactive.
- Capacity mechanism
- none in 2025 ACER, Security of EU electricity supply, 2025 Monitoring Report, p. 12, 20 Nov 2025
- Minimum size to offer balancing services
- 1 MW, alone or aggregated EWRC report on storage and industrial consumers in the balancing market, 21 Aug 2026
- Registered balancing service providers, end-2025
- 22, including 1 industrial consumer (inactive) EWRC report on storage and industrial consumers in the balancing market, 21 Aug 2026
Source: ACER, Security of EU electricity supply, 20 Nov 2025
Legal texts: ACER, Security of EU electricity supply 2025
Next dated changeDated30 Jun 2027: the second price period ends, the last month in which aid for July 2025 to June 2026 consumption can be paid.
The second price period of the CISAF scheme runs to 30 June 2027, with a €50/MWh floor and a budget of up to €170m. Aid is due in the price period the cost arises or the next one, so aid for July 2025 to June 2026 consumption can be paid only until that date. Firms with several activities then have two months to file audited cost splits with the Ministry of Energy. The general programme's ten-month period also ends on 30 June 2027; the government then sets the share of the price above €122.71/MWh it compensates, up to 80%, and pays by 31 December 2027. On 4 November 2026 the Ministry of Energy said the aid intensity for energy-intensive users could rise from 50% to 70% after a new notification to the Commission.
- Second price period ends
- 30 Jun 2027 Council of Ministers Decision No 706, 9 Sep 2026
- Last month to pay aid on July 2025 to June 2026 consumption
- Jun 2027 Decree No 237/2025, art. 11(3), 11 Nov 2025
- General programme: rate set, then paid
- after 30 Jun 2027; by 31 Dec 2027 Council of Ministers Decision No 730, Annex 1, 18 Sep 2026
- Aid intensity under discussion
- 70%, after a new notification Ministry of Energy press release, 4 Nov 2026
Source: Decree No 237/2025, art. 11(3)
Legal texts: Министерство на енергетиката, 4 Nov 2026
Checked 11 Nov 2026. Not legal, tax or investment advice.
Country profile
Germany
Germany's Industriestrompreis cuts power costs on half of eligible consumption until 2028, while grid fees change from 2029.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Gross electricity consumption: AG Energiebilanzen, Stromerzeugung nach Energieträgern 1990 bis 2025 (xlsx, row 'Bruttostromverbrauch inkl. PSE'), 7 Oct 2026. Transmission grid fee, average: Four TSOs, press release on preliminary grid fees 2026, 1 Oct 2025.
Policies
Price relief (CISAF 4.5)In forceGermany's Industriestrompreis pays back part of eligible industry's power costs for 2026 to 2028, with €3.8bn of funding.What it means: An eligible site gets relief on half of its consumption, but must reinvest half of the basic aid.
Sites in sectors the EU lists as at risk of relocation get part of their 2026 to 2028 power costs back the year after. On half of eligible consumption, the aid brings the 2026 reference price of €87.44/MWh down to €50/MWh. At least half the basic aid must be reinvested within 48 months of the grant decision.
- Budget 2026 to 2028
- €3.8bn European Commission decision C(2026) 2584 final, SA.120495, 16 Apr 2026
- Aid in 2026, on half of eligible consumption
- €37.44/MWh BAFA programme page Industriestrompreis, undated, checked 6 Nov 2026
- Application deadline, 2026
- 31 Mar 2027 (15 Jul 2027 with Strompreiskompensation) BAFA programme page Industriestrompreis, undated, checked 28 Sep 2026
Source: BAFA programme page
Legal texts: Industriestrompreis (BAnz AT 06.05.2026 B1)
CO₂ cost compensationIn forceStrompreiskompensation refunds part of the CO₂ cost built into power prices, and more sectors qualify since July 2026.What it means: Sites in the newly added sectors may now be eligible. Claims for 2026 costs close between 31 May and 30 Sep 2027; DEHSt has not set the date.
Strompreiskompensation, widened to more sectors in July 2026. Claims for 2025 costs closed on 17 Aug 2026; claims for 2026 costs close between 31 May and 30 Sep 2027.
The Strompreiskompensation refunds part of the carbon cost passed into power prices to manufacturers in sectors listed in the EU ETS State aid Guidelines. Under the July 2026 rules, 20 added sectors and 2 subsectors receive 75% of eligible costs for 2025 and the original sectors 80%. For 2026 costs the guideline sets 75% for all sectors and reserves a further amendment for 2026 to 2030. Applications for 2025 costs closed on 17 August 2026. The deadline for 2026 costs falls between 31 May and 30 September 2027 and is not yet set. Under the guideline in force, power claimed here cannot also count under the Industriestrompreis; no amendment had been published by 31 Oct 2026.
- Aid intensity, 2025 costs
- 80% (original sectors); 75% (22 added sectors) Billigkeitsrichtlinie indirekte CO2-Kosten, BAnz AT 22.07.2026 B1, Nr. 7.2, 22 Jul 2026
- Aid intensity, 2026 costs
- 75% (a further amendment for 2026 to 2030 is reserved) Billigkeitsrichtlinie indirekte CO2-Kosten, BAnz AT 22.07.2026 B1, Nr. 5.1 h and Nr. 2, 22 Jul 2026
- Federal budget for applications in 2026
- €4bn DEHSt, SPK verstehen, updated 2026-06-29
- EUA price used for 2025 costs
- €68.86/t DEHSt, SPK verstehen, updated 2026-06-29
Source: DEHSt, 19 Aug 2026
Legal texts: Strompreiskompensation
Grid fee reliefEndingDiscounted individual grid fees for large, steady consumers under §19(2) StromNEV end on 31 Dec 2028.What it means: Sites on these discounts lose them from 2029. The draft extends existing agreements to 2031 for sites above 10 GWh a year.
§19(2) StromNEV individual grid fees end on 31 Dec 2028. BNetzA's draft extends existing atypical-use and band-load agreements to 31 Dec 2031 for sites above 10 GWh a year.
Under §19(2) StromNEV, grid operators must offer individual fees to two groups. Sites whose peak falls outside the grid's high-load windows (atypical use) pay no less than 20% of the published fee. Sites drawing over 10 GWh a year with at least 7,000 full-load hours (band load) pay no less than 20%, 15% or 10%, depending on their hours. The ordinance expires on 31 December 2028. BNetzA's August 2026 draft keeps both discounts to 31 December 2031 for agreements in force at the end of 2028 that qualified at least once in 2026 to 2028. For atypical use it adds a test of average consumption above 10 GWh a year in 2024 to 2027, and freezes the discount at its 2024 to 2027 average. The draft is not final; BNetzA plans to adopt it in 2026.
- Lowest possible fee, band load at 8,000 hours or more
- 10% of the published fee §19(2) StromNEV (consolidated), Stand 2023-12-22
- Ordinance expires
- 31 Dec 2028 Gesetz vom 22.12.2023, BGBl. 2023 I Nr. 405, Art. 15(3), 28 Dec 2023
- Draft transition for existing agreements
- to 31 Dec 2031 (draft) BNetzA, AgNes draft determination GBK-25-01-1#3 (draft, not final), 6 Aug 2026
Source: BNetzA, AgNes consultation
Legal texts: §19(2) StromNEV
Storage rulesIn force§118(6) EnWG: no grid fees on stored energy for 20 years if commissioned by 4 Aug 2029. The AgNes draft adds an investment-decision cut-off of 31 Dec 2026.
§118(6) EnWG exempts new storage from grid fees on the electricity it draws, for 20 years from commissioning. The plant must start operating by 4 August 2029. The exemption applies only to the extent that stored energy is fed back into the same grid. BNetzA's August 2026 AgNes draft would keep it only for projects with a final investment decision before 1 January 2027, proven by 31 March 2027. Other storage would pay new grid fees from 2029.
- Exemption period
- 20 years from commissioning §118(6) EnWG (consolidated), current, retrieved 2026-10-08
- Commissioning deadline
- 4 Aug 2029 §118(6) EnWG (consolidated), current, retrieved 2026-10-08
- Final investment decision cut-off
- before 1 Jan 2027, proof by 31 Mar 2027 (draft) BNetzA, AgNes draft determination GBK-25-01-1#3 (draft, not final), 6 Aug 2026
Source: §118 EnWG
Legal texts: §118(6) EnWG
Capacity mechanismIn forceStromVKG tenders for capacity from Nov 2031. New storage can bid from 18 May 2027, or from 29 Dec 2026 with 10-hour output; flexible demand from 1 Dec 2027.
The StromVKG, in force since 22 July 2026, buys capacity to be available from 1 November 2031 and counts storage as a generation plant. Two 2026 tenders for new long-duration capacity, on 8 September and 29 December with 4.5 GW each, accept only plants that can feed in 80% of their capacity for 10 hours in a row, on 15-year terms. BNetzA awarded the first on 3 November 2026: 5,160 derated MW at a volume-weighted average of €155,296 per MW a year. A 2 GW tender on 18 May 2027 is open to all generation plants, including batteries, with no 10-hour rule, also on 15-year terms. Tenders on 1 December 2027 and 1 October 2029 add flexible demand and existing plants, with terms of one, seven or 15 years. Their volumes are not yet set.
- Volume per 2026 tender (generation only)
- 4.5 GW BNetzA, Ausschreibungen nach dem StromVKG, Stand 2026-07-21
- Capacity tender dates
- 1 Dec 2027 and 1 Oct 2029 Gleiss Lutz, StromVKG: neuer Kapazitätsmechanismus (law-firm summary, secondary), 5 Oct 2026
- Commitment periods in capacity tenders
- 1, 7 or 15 years Gleiss Lutz, StromVKG: neuer Kapazitätsmechanismus (law-firm summary, secondary), 5 Oct 2026
Source: StromVKG, 21 Jul 2026
Legal texts: StromVKG
Next dated changeDatedDec 2026: Industriestrompreis portal expected to open. End 2026: final AgNes decision expected.
Three dated steps are tracked. Registration on the Förderzentrale Deutschland portal is expected from December 2026, and applications for 2026 are filed in 2027. The deadline is 31 March 2027, or 15 July 2027 for firms also claiming CO₂ cost compensation. BNetzA plans its final AgNes decision for 2026 and has fixed 1 January 2027 as the date of announcement. On the draft, storage needs a final investment decision before that date to keep its grid-fee exemption.
- Industriestrompreis portal registration opens
- expected Dec 2026 BAFA programme page Industriestrompreis, undated, checked 6 Nov 2026
- Industriestrompreis application deadline, 2026
- 31 Mar 2027 BAFA programme page Industriestrompreis, undated, checked 28 Sep 2026
- AgNes date of announcement
- 1 Jan 2027 (draft) BNetzA, AgNes draft determination GBK-25-01-1#3 (draft, not final), 6 Aug 2026
Source: BAFA programme page
What it means for you
Which measures apply in Germany depends on a company's sector and annual consumption
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
Spain
Spain has no EU price-relief scheme and lowers industrial costs through its electro-intensive statute and a 2026 toll cut.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand (REE): Red Eléctrica, press release on Informe del sistema eléctrico español 2025, 11 Mar 2026. Network toll, 6.1TD peak period: CNMC Resolución de 18 de diciembre de 2025, peajes 2026, BOE-A-2025-26348, Anexo I, 22 Dec 2025.
Policies
Price relief (CISAF 4.5)NoneSpain has no CISAF price-relief scheme. The electro-intensive statute compensates part of the system charges instead.What it means: Only certified electro-intensive sites get compensation, and it covers system charges, not the power price.
No CISAF 4.5 scheme. The electro-intensive statute compensates part of the system charges instead.
Spain has no scheme under CISAF section 4.5, and none had been notified or announced by 8 October 2026. Instead, the electro-intensive statute pays certified sites a yearly grant. It covers up to 85% of the system charges that fund renewables, cogeneration and island systems, or 75% in lower-risk sectors. The 2026 call had €11.9m against €19.34m claimed, so awards were prorated. A reform approved by the Commission in July 2026 was not yet in the BOE in October.
- Maximum grant intensity
- 85% of eligible charges (75% in 'riesgo' sectors) RD 1106/2020, art. 20.4 (consolidated, BOE), consolidated 2026-03-21
- 2026 grant call budget
- €11.9m Extracto convocatoria electrointensivos 2026, BOE-B-2026-16934, 23 May 2026
- Eligibility ratio, 2026
- consumption above 0.61 kWh per € of gross value added Resolución de 16 de enero de 2026, BOE-A-2026-1469, 21 Jan 2026
Source: BOE, RD 1106/2020 (consolidated)
Legal texts: Estatuto electrointensivo (RD 1106/2020)
CO₂ cost compensationIn forceSpain refunds part of the CO₂ cost built into power prices. The 2026 call covered 2025 costs with €600m.What it means: The 2026 call is closed, so eligible sites wait for the next call.
Indirect-cost compensation. The 2026 call (2025 costs, €600m) is closed.
Spain refunds part of the carbon cost passed into power prices to firms in sectors listed by the EU ETS Guidelines. From the 2026 call, the original sectors receive up to 80% of indirect costs and 22 newly added sectors 75%. The 2026 call covered 2025 costs, had a budget of €600m and ran from 30 July to 26 August 2026. Payments are prorated to the budget. The 2025 call paid out €597.9m.
- 2026 call budget (2025 costs)
- €600m Extracto convocatoria compensación costes indirectos 2026, BOE-B-2026-25588, 29 Jul 2026
- Maximum aid intensity
- 80% (original sectors); 75% (added sectors) Orden PJC/678/2026, BOE-A-2026-14655, 7 Jul 2026
- Paid under 2025 call
- €597.9m MINTUR, Resolución de concesión CO2 2025, 25 Nov 2025
Source: BOE-B-2026-25588, 29 Jul 2026
Legal texts: Compensación de costes indirectos (RD 309/2022)
Grid fee relief2026 onlyCertified electro-intensive sites pay 80% less in network tolls until 31 Dec 2026.What it means: Unless the cut is extended, these sites return to full tolls in January 2027, five times what they pay now.
80% cut in network tolls for sites with the electro-intensive certificate, ending 31 Dec 2026.
For all of 2026, sites holding the electro-intensive certificate pay only 20% of network access tolls. The decree took effect on 22 March but applies from 1 January: the discount for the weeks before was credited separately on the first bill after that date. The cut applies to both power and energy terms, in every time period, and appears as a discount on the bill. No application is needed. It does not cover system charges. A State credit of €220m funds it. The measure has been renewed year by year since 2022, with gaps in 2025. Nothing is published beyond 31 December 2026.
- Cut in network tolls
- 80% Real Decreto-ley 7/2026, BOE-A-2026-6544, 21 Mar 2026
- State credit
- €220m Real Decreto-ley 7/2026, BOE-A-2026-6544, 21 Mar 2026
- End date
- 31 Dec 2026 Real Decreto-ley 7/2026, BOE-A-2026-6544, 21 Mar 2026
Source: BOE, RDL 7/2026, art. 7
Legal texts: RDL 7/2026
Storage rulesIn forceSelf-consumption rules let the generator owner differ from the consumer and allow storage behind the same meter. Battery ownership is not stated.
RD 244/2019 allows storage inside self-consumption installations if it meets industrial safety rules and shares a meter with net generation, the boundary point or the consumer. Grid-connected batteries pay no tolls, and no charges on energy later fed back to the grid. A battery behind a consumer's meter is billed as part of that consumer's supply. In 2026 the CNMC confirmed that consumers may hold storage on their internal network. A draft decree on distributed storage is not yet adopted.
- Storage demand access handled as flexible access
- from 1 Sep 2026 (types 0 and 1) CNMC Resolución de 31.07.2026 (acceso flexible de demanda), BOE-A-2026-17571, 11 Aug 2026
Source: BOE, RD 244/2019, art. 5
Legal texts: Autoconsumo (RD 244/2019)
Capacity mechanismAdoptedOrden TED/966/2026: consumers and storage from 1 MW can take part. No auction has been called and no date is set.
Orden TED/966/2026 created Spain's capacity market, in force since 18 September 2026. Red Eléctrica will run pay-as-bid auctions for firm capacity. Generators, storage and consumers can take part from 1 MW, smaller sites through aggregation. Demand chooses contracts of one to ten years, capped at the site's lowest contracted power. Calls fall in stress hours, at most 10% of the year. The Commission estimates about €900m a year. No auction had been called by 3 November 2026.
- Minimum firm capacity per installation or aggregation
- 1 MW Orden TED/966/2026, BOE-A-2026-19329, 17 Sep 2026
- Stress hours
- at most 10% of the hours in a year Orden TED/966/2026, BOE-A-2026-19329, 17 Sep 2026
- Estimated cost
- about €900m a year European Commission press release IP/26/1163 (SA.112483), 29 May 2026
Source: BOE, 17 Sep 2026
Legal texts: Mercado de capacidad (Orden TED/966/2026)
Demand responseIn forceSites cut load within 12.5 minutes when called; offers start at 1 MW, from one site or aggregated. H2 2026 cleared at €42.62/MW per hour; next auction 26 Nov 2026.
SRAD runs under P.O. 7.5 of November 2025, as amended in May 2026. Offers start at 1 MW, from one site above 1 MW or aggregated smaller sites. A unit must draw at least its awarded MW in every service hour. When called, it cuts load within 12.5 minutes for up to two hours, at most once a day. Availability is paid at the marginal price per MW and hour. By 3 November, SRAD had been called on 8 days in 2026. The next auction is on 26 November 2026.
- Latest auction, 28 May 2026 (delivery 1 Jul to 31 Dec 2026)
- 1,775 MW at €42.62/MW per hour REE, nota de prensa SRAD segundo semestre 2026, 28 May 2026
- Previous auction, 28 Nov 2025 (delivery 1 Jan to 30 Jun 2026)
- 1,725 MW at €65/MW per hour REE, nota de prensa SRAD primer semestre 2026, 28 Nov 2025
- Next auction (delivery 1 Jan to 30 Jun 2027)
- 26 Nov 2026; requirement 2,405 MW REE e·sios, Publicación de la información referente al SRAD S1 2027, 26 Oct 2026
- Activations since 1 Jul 2026
- 9 calls on 7 days, 15 Jul to 6 Oct 2026 REE e·sios, activaciones del servicio SRAD, accessed 2026-11-03
Source: REE, e·sios SRAD page (P.O. 7.5)
Legal texts: Servicio de respuesta activa de la demanda, P.O. 7.5 (BOE-A-2025-22853) · Modificación del P.O. 7.5 (BOE-A-2026-10602) · SRAD en e·sios: subastas y activaciones
Next dated changeDated31 Dec 2026: the 80% toll cut for certified electro-intensive sites ends; no extension has been published. No date is set for the first capacity auction.
Two 2026 measures end on 31 December 2026 unless extended: the 80% toll cut for electro-intensive sites and the freedom to change contracted power without the 12-month lock. No extension had been published by 3 November 2026. A reform of the electro-intensive statute, approved by the Commission on 31 July 2026, awaits publication in the BOE. No official date for the first capacity auction has been published.
- Toll cut ends
- 31 Dec 2026 Real Decreto-ley 7/2026, BOE-A-2026-6544, 21 Mar 2026
- Contracted-power flexibility ends
- 31 Dec 2026 Real Decreto-ley 7/2026, BOE-A-2026-6544, 21 Mar 2026
- Commission approval of statute reform
- 31 Jul 2026 European Commission decision SA.123095, 31 Jul 2026
Source: BOE, RDL 7/2026, art. 7
What it means for you
Which measures apply in Spain depends on a company's sector and annual consumption
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
France
France has no EU price-relief scheme, and its new capacity mechanism starts delivery on 1 November 2026.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Gross electricity consumption (RTE): RTE, Bilan électrique 2025, principaux résultats, Feb 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c (electricity price components for non-household consumers), 16 Oct 2026.
Policies
Price relief (CISAF 4.5)None foundNo CISAF price-relief scheme found. France's CISAF scheme SA.122265 supports manufacturing investment instead.What it means: French support under the framework goes to investment projects, not to the power bill.
No CISAF 4.5 price-relief scheme found. France's €380m CISAF scheme SA.122265, open until 31 Dec 2030, supports clean-tech manufacturing investment.
We found no French scheme under CISAF section 4.5, which allows governments to cut the electricity price paid by energy-intensive users. France's CISAF scheme SA.122265 serves another purpose. It supports investment in the production of specified finished products, key components and raw materials. The budget is €380 million and aid can be granted until 31 December 2030. The decision was published in the EU Official Journal on 11 June 2026.
- SA.122265 budget (investment aid, not price relief)
- €380 million EU Official Journal C/2026/3108, 11 Jun 2026
- SA.122265 aid may be granted until
- 31 Dec 2030 EU Official Journal C/2026/3108, 11 Jun 2026
CO₂ cost compensationIn forceCompensation carbone refunds part of the CO₂ cost built into power prices, and 13 more sectors qualify for 2025 costs.What it means: The 2027 finance bill, before Parliament, budgets €814m to keep it for 2026 costs.
Compensation carbone at 75% of eligible costs, extended to 13 more sectors for 2025 costs (decree of 2 Nov 2026). The 2027 finance bill budgets €814m for 2026 costs.
France refunds part of the carbon cost in power prices through the compensation carbone. Decree 2026-1021 of 2 November 2026 extends it to 13 more sectors, including organic chemistry and fertilisers, for 2025 costs; the government put that extension at €150 million for about 100 chemical sites. The aid stays at 75% of eligible costs. The decree fixes the emission factor at 0.51 tCO₂/MWh only for costs up to 2025, and the aid is now paid in the year after the costs, without an advance. The 2027 finance bill, tabled on 1 October 2026, keeps the scheme with €814.1 million for 2026 costs. Parliament has not yet adopted the bill.
- Aid intensity
- 75% of eligible costs, 2021 to 2030 Décret n° 2026-1021 du 2 novembre 2026, art. D. 122-18, 2 Nov 2026
- Budget for the 2026 extension (2025 costs) to organic chemistry and fertilisers
- €150 million Assemblée nationale, written question 14875, ministerial answer, 7 Jul 2026
- Chemical sites benefiting from the extension
- about 100 Assemblée nationale, written question 14875, ministerial answer, 7 Jul 2026
Source: PLF 2027, Économie annex, 1 Oct 2026
Legal texts: Décret n° 2026-1021 du 2 novembre 2026 · Compensation carbone
Grid fee reliefIn forceTURPE 7 has reduced transmission tariffs for high-consumption sites since 1 Aug 2025.What it means: High-consumption sites on the transmission grid already pay lower network tariffs.
TURPE 7, in force since 1 Aug 2025, reduces transmission tariffs for high-consumption sites.
Sites that consume a lot of electricity with a stable, predictable or counter-cyclical profile pay reduced transmission tariffs. The reduction comes from article L. 341-4-2 of the Energy Code, with rates set by decree. The TURPE 7 transmission tariff, in force since 1 August 2025 for about four years, builds the lost revenue into RTE's tariff. CRE estimates the reduction at €311.0 million in 2025, rising to €532.3 million in 2028.
- TURPE 7 HTB in force from
- 1 Aug 2025 (about four years) CRE deliberation 2025-39, 4 Feb 2025
- Estimated value of the electro-intensive reduction, 2025
- €311.0 million CRE deliberation 2025-39, table 48, 4 Feb 2025
- Estimated value of the electro-intensive reduction, 2028
- €532.3 million CRE deliberation 2025-39, table 48, 4 Feb 2025
Source: CRE deliberation 2025-77, 13 Mar 2025
Legal texts: TURPE 7 (CRE)
Storage rulesIn forceSince 1 Aug 2026, stand-alone storage in CRE-listed zones can opt for a storage tariff. Batteries combined with a consumption or production site, such as a factory, are excluded.
TURPE 7 adds an optional injection and withdrawal component for storage, available since 1 August 2026. It replaces the normal withdrawal charge and rewards charging or discharging against local grid peaks. It applies at HTA, HTB 1 and HTB 2 voltage, in network zones listed by CRE on 1 October 2025. Only stand-alone storage that draws from and returns all its energy to the public grid qualifies. Storage combined with a consumption or production site, such as a battery behind an industrial meter, is excluded.
- Voltage levels eligible
- HTA, HTB 1 and HTB 2 CRE deliberations 2025-77 (s. 4.4.2.4) and 2025-78, 13 Mar 2025
- Storage tariff available from
- 1 Aug 2026 CRE deliberation 2025-77, s. 4.4.2.7, 13 Mar 2025
- Eligible zones fixed
- 1 Oct 2025 CRE deliberation 2025-227, 1 Oct 2025
Capacity mechanismIn forceNew centralised mechanism (Décret 2025-1441). First auction held 6 Jul 2026; demand response and storage can take part.
France replaced its capacity mechanism with a centralised one run by RTE, set out in Decree 2025-1441. Production, storage and demand response can take part. The only auction for winter 2026 to 2027 was held on 6 July 2026. It cleared at €28,182.99 per MW and contracted 82,446.8 MW. A reserved 4,700 MW for low-carbon flexibility, meaning batteries, pumped hydro and demand response, cleared separately at €14,967.2 per MW.
- Clearing price, delivery period 2026-27
- €28,182.99/MW RTE, auction report for delivery period 2026/2027, 17 Jul 2026
- Volume contracted
- 82,446.8 MW RTE, auction report for delivery period 2026/2027, 17 Jul 2026
- Reserved low-carbon flexibility volume and price
- 4,700 MW at €14,967.2/MW RTE, auction report for delivery period 2026/2027, 17 Jul 2026
Source: CRE deliberation 2026-143, 9 Jul 2026
Legal texts: Mécanisme de capacité (Décret 2025-1441)
Next dated changeDatedThe first capacity delivery period runs from 1 Nov 2026 to 31 Mar 2027. The 2027 finance bill, before Parliament, budgets €814m to keep carbon compensation, covering 2026 costs.
The first delivery period of the new capacity mechanism runs from 1 November 2026 to 31 March 2027. Contracted capacity must be available over that winter, and the cost is passed to consumers through a tax based on consumption. Separately, the 2027 finance bill, tabled in the Assemblée nationale on 1 October 2026, keeps carbon compensation. Its budget annex sets aside €814.1 million for 2027, covering indirect costs incurred in 2026 at 75%, with a possible top-up for the most electricity-intensive companies. It does not say whether the 2026 extension to organic chemistry and fertilisers continues. Parliament has not yet adopted the bill.
- First delivery period
- 1 Nov 2026 to 31 Mar 2027 RTE, auction report for delivery period 2026/2027, 17 Jul 2026
- Carbon compensation budgeted for 2027 (2026 costs)
- €814.1 million PLF 2027, Économie annex, programme 134, 1 Oct 2026
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
Ireland
Ireland has the highest industrial power price of the nine markets and a €300m price-relief scheme approved in July 2026.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand, Ireland (EirGrid): EirGrid, System and Renewable Data Summary Report V30 (xlsx, sheet 'Fuel Mix & CO2', calendar-year table), 22 Sep 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)In forceIreland's temporary electricity price relief, approved on 16 Jul 2026, has an estimated €300m for 2025 to 2029. No call for applications found by 11 Nov 2026.What it means: Eligible sites would get relief on half of their consumption for up to three years, and must reinvest half of the aid.
Temporary electricity price relief (SA.120348), an estimated €300m for 2025 to 2029, approved on 16 Jul 2026. No call for applications found by 11 Nov 2026.
Ireland's scheme implements CISAF section 4.5 for companies in the sectors listed in Annex 1 of the Commission's 2022 climate, energy and environment aid guidelines (CEEAG). Each year a company receives a direct grant worth half the yearly average day-ahead price for Ireland and Northern Ireland, on half the electricity its eligible activities used in the previous 12 months, measured at the grid connection point. The price after aid may not fall below €50 per MWh. A company can receive aid for at most three years, and final payments are due by 31 December 2030. At least half of the aid must be invested in renewables, storage, demand-side flexibility, efficiency, electrolysers or electrification, in operation within 48 months. IDA Ireland and Enterprise Ireland grant the aid; no call for applications had been found by 11 November 2026.
- Estimated maximum budget
- €300m over the scheme's duration European Commission, decision C(2026) 4889 (SA.120348), recital 28, 16 Jul 2026
- Maximum support
- 50% of the yearly average day-ahead price on 50% of eligible consumption; price after aid not below €50/MWh European Commission, decision C(2026) 4889 (SA.120348), recitals 9 and 10, 16 Jul 2026
- Scheme period
- 4 Jul 2025 to 31 Dec 2029; at most three years per company; final payments by 31 Dec 2030 European Commission, decision C(2026) 4889 (SA.120348), recitals 26 and 27, 16 Jul 2026
- Reinvestment condition
- At least 50% of the aid, in operation within 48 months European Commission, decision C(2026) 4889 (SA.120348), recitals 15 and 16, 16 Jul 2026
- Granting authorities
- IDA Ireland and Enterprise Ireland European Commission, decision C(2026) 4889 (SA.120348), recital 21, 16 Jul 2026
Source: European Commission, C(2026) 4889, 16 Jul 2026
Legal texts: European Commission press release IP/26/1610 (16 Jul 2026) · SA.120348 case page (European Commission) · Temporary electricity price relief (SA.120348) · PSO Levy 2026/27 (CRU2026107)
CO₂ cost compensationNoneIreland has no scheme refunding the CO₂ cost built into power prices, and has told the Commission it plans none.What it means: Irish sites recover none of the CO₂ cost passed into their power price.
No indirect-cost compensation. Ireland told the Commission in 2026 that it has no such scheme and no plans to introduce one.
Ireland does not compensate electricity-intensive companies for the EU ETS costs passed into electricity prices. In the procedure for its price-relief scheme, approved on 16 July 2026, Ireland confirmed to the Commission that no indirect-cost compensation measure under the post-2021 ETS State aid guidelines is in place and that there are no plans to introduce one.
- Indirect-cost compensation scheme
- None in place and none planned European Commission, decision C(2026) 4889 (SA.120348), recital 32, 16 Jul 2026
Grid fee reliefNoneIreland gives large users no network-charge or PSO levy relief. Large Energy User rebalancing ended in 2022.What it means: Large sites pay standard network tariffs. The PSO levy falls to €0.24/kVA a month from 1 Oct 2026.
No network-charge or PSO levy relief for large users. The CRU ended Large Energy User rebalancing of network tariffs on 1 Oct 2022.
Ireland has no reduction of network charges or of the PSO levy for large or energy-intensive users. The CRU ended Large Energy User rebalancing, which had shifted network costs from large users to domestic customers, from 1 October 2022; large users then repaid a €100.86m implementation error through higher tariffs from 2023/24 to 2025/26. In 2026/27 the CRU's large non-domestic example (25 GWh a year, 10 MVA) pays 5.1% less in distribution charges, as the last repayment drops out, and 1% less in transmission charges. From 1 October 2026 the PSO levy for customers of 30 kVA and above falls 66% to €0.24 per kVA a month. Electricity used for chemical reduction or in electrolytic or metallurgical processes is relieved of electricity tax, charged at €1 per MWh on business use, by repayment.
- Large Energy User rebalancing ended
- From 1 Oct 2022 (2022/23 tariff year) CRU, CRU2026108, Appendix E, 29 Jul 2026
- Distribution charges 2026/27, large non-domestic example (25 GWh a year, 10 MVA)
- €615,605 (-5.1%) CRU, CRU2026108, table 3, 29 Jul 2026
- Transmission charges 2026/27, same example
- €911,882 (-1%) CRU, CRU2026112, table 8, 29 Jul 2026
- PSO levy from 1 Oct 2026, customers of 30 kVA and above
- €0.24/kVA a month (€0.70 in 2025/26) CRU, PSO Levy 2026/27 Decision Paper (CRU2026107), 29 Jul 2026
- Electricity tax, business use
- €1/MWh; repaid on electricity used for chemical reduction or in electrolytic or metallurgical processes Revenue, Electricity Tax: reliefs and rates, 6 Aug 2026
Source: CRU, CRU2026108, 29 Jul 2026
Legal texts: CRU, 2026/27 network charges and PSO levy (29 Jul 2026)
Storage rulesIn forceA battery co-located with demand keeps the site's demand network charges; only standalone and generation-sited storage moved to generator charges on 1 Oct 2026. S.I. 76/2022 bars double charges on stored power kept on site.
Under an interim CRU decision, standalone batteries and batteries co-located with generation have paid generator transmission charges instead of demand charges since 1 October 2026. Batteries co-located with demand, such as at a factory, and autoproducers see no change, so the energy they draw carries the site's demand network charges. The CRU will revisit storage charging in its multi-annual network tariff structure review. Under S.I. No. 76 of 2022, active customers that own storage may not be charged twice, including network charges, for stored electricity that stays on their premises. Active customers may delegate the management of their installations to a third party, and a renewables self-consumer's installation may be owned by a third party.
- Standalone and generation-sited storage
- Generator transmission charges from 1 Oct 2026 (interim) CRU, CRU/2026/96, 16 Jun 2026
- Storage co-located with demand
- No change: demand network charges CRU, CRU/2026/96, table 1, 16 Jun 2026
- Double charges on stored electricity kept on site
- Not allowed for active customers that own storage S.I. No. 76 of 2022, reg. 3(3)(b), 15 Feb 2022
- Third parties
- May manage an active customer's installation; may own a renewables self-consumer's installation S.I. No. 76 of 2022, regs. 3(2)(e) and 4(5), 15 Feb 2022
Source: CRU, CRU/2026/96, 16 Jun 2026
Legal texts: CRU/2026/96, Interim Transmission Network Charges for Energy Storage · S.I. No. 76 of 2022
Capacity mechanismIn forceAll-island capacity market run by EirGrid and SONI, open to Demand Side Units and batteries. The 2029/30 T-4 auction cleared at €135,499.99 per de-rated MW a year.
EirGrid and SONI run T-4 and T-1 auctions for the capacity market of the all-island Single Electricity Market. The 2029/30 T-4 auction cleared at €135,499.99 per de-rated MW a year and awarded 3,862 MW, including 332 MW of Demand Side Units and 39 MW of batteries. The 2026/27 T-1 auction cleared at €53,978.87 per MW a year and awarded 377 MW. Capacity counts after de-rating: for the 2030/31 T-4 auction, a battery of up to 10 MW is de-rated to 0.084 with 2 hours of storage, 0.162 with 4 hours and 0.563 with 8 hours. That auction runs on 25 March 2027.
- Clearing price, 2029/30 T-4 auction
- €135,499.99 per de-rated MW a year EirGrid and SONI, FCAR2930T-4, 5 May 2026
- Awarded, 2029/30 T-4 auction
- 3,862.323 MW; Demand Side Units 331.825 MW; batteries 38.752 MW EirGrid and SONI, FCAR2930T-4, 5 May 2026
- Clearing price and award, 2026/27 T-1 auction
- €53,978.87 per MW a year; 377.16 MW EirGrid and SONI, FCAR2627T-1, 26 Aug 2026
- Battery de-rating factors, 2030/31 T-4, up to 10 MW
- 2 h: 0.084; 4 h: 0.162; 8 h: 0.563 EirGrid and SONI, IAIP3031T-4, table 3, 4 Aug 2026
- Next T-4 auction (2030/31)
- 25 Mar 2027; results 30 Apr 2027 SEMO, CAT3031T-4 v1.1, 6 Nov 2026
Source: EirGrid and SONI, FCAR2930T-4, 5 May 2026
Legal texts: SEMO, Capacity Auction Timetable · Capacity Market Code (SEMO)
Demand responseIn forceDemand Side Units of at least 4 MW, from one site or aggregated, cut load when EirGrid instructs and earn capacity payments.
A Demand Side Unit is one or more demand sites, typically medium to large industrial premises, that reduce consumption when EirGrid instructs, using on-site generation, plant shutdown or both. DSUs available for demand reduction are eligible for capacity payments in the Single Electricity Market. A DSU needs at least 4 MW of demand reduction; a site of 10 MW or more registers on its own, while smaller sites join through an aggregator that is a licensed supplier. In the 2029/30 T-4 auction, 54 DSUs won 331.8 MW; in the 2026/27 T-1 auction, DSUs won 57.4 MW.
- Minimum DSU size
- 4 MW of demand reduction; sites of 10 MW or more register alone EirGrid, Demand Side Management page, accessed 2026-11-11
- DSU capacity awarded, 2029/30 T-4 auction
- 331.825 MW across 54 units EirGrid and SONI, FCAR2930T-4, 5 May 2026
- DSU capacity awarded, 2026/27 T-1 auction
- 57.382 MW EirGrid and SONI, FCAR2627T-1, 26 Aug 2026
Source: EirGrid, Demand Side Management page
Legal texts: EirGrid, Demand Side Management
Next dated changeDated3 Dec 2026: last day to register a proposed new unit for the 2027/28 T-1 capacity auction, held on 24 Jun 2027. The 2030/31 T-4 auction runs on 25 Mar 2027.
Proposed new units for the 2027/28 T-1 capacity auction must be provisionally registered by 3 December 2026. Qualification applications run from 7 to 22 January 2027, the auction runs on 24 June 2027 and results are due on 30 July 2027. The 2030/31 T-4 auction runs earlier, on 25 March 2027, with results on 30 April 2027. The regulated tariffs for DS3 system services end when day-ahead system services auctions go live, and no later than 30 September 2027.
- Registration of proposed new units closes, 2027/28 T-1 auction
- 3 Dec 2026 SEMO, CAT2728T-1 v1.0, 2 Oct 2026
- 2027/28 T-1 auction; results
- 24 Jun 2027; 30 Jul 2027 SEMO, CAT2728T-1 v1.0, 2 Oct 2026
- 2030/31 T-4 auction; results
- 25 Mar 2027; 30 Apr 2027 SEMO, CAT3031T-4 v1.1, 6 Nov 2026
- End of regulated DS3 system services tariffs
- At day-ahead auction go-live, no later than 30 Sep 2027 SEM Committee, SEM-25-031, 23 Jun 2025
Source: SEMO, CAT2728T-1, 2 Oct 2026
Legal texts: SEMO, Capacity Auction Timetable
Checked 11 Nov 2026. Not legal, tax or investment advice.
Country profile
Italy
Italy has the second-highest industrial power price of the nine markets and raised its CO₂ compensation budget to €3.6bn in 2026.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand (Terna, provisional): Terna, 'Nel 2025 fabbisogno elettrico pari a 311,3 TWh', 21 Jan 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)None foundNo CISAF price-relief scheme found. Energy Release 2.0 runs outside that framework.What it means: Italian power-cost relief for industry comes through Energy Release 2.0, not a CISAF scheme.
No CISAF 4.5 scheme found. Energy Release 2.0, outside that section, advances renewable power to energy-intensive users at €65/MWh for 2025 to 2027.
We found no Italian scheme under CISAF section 4.5. Italy's main tool for energy-intensive users is Energy Release 2.0, which sits outside that section. The state energy agency GSE advances renewable electricity to energy-intensive companies for 2025 to 2027 at €65 per MWh. In return, companies must build new renewable capacity and give the energy back over 20 years. Italy amended the scheme in July 2025 to meet conditions set by the Commission in a letter of 27 June 2025.
- Energy Release 2.0 transfer price
- €65/MWh MASE directorial decree 104 of 17 Dec 2025, Annex 1, 17 Dec 2025
- Advance period
- 2025 to 2027 MASE directorial decree 104 of 17 Dec 2025, Annex 1, 17 Dec 2025
- Repayment period
- 20 years from plant commissioning MASE directorial decree 104 of 17 Dec 2025, Annex 1, 17 Dec 2025
CO₂ cost compensationIn forceItaly raised its CO₂ cost compensation budget from €1.5bn to €3.6bn and the aid intensity to 80%.What it means: Eligible sites can recover up to 80% of their eligible indirect CO₂ costs.
Budget raised from €1.5bn to €3.6bn and aid intensity to 80% (SA.122463).
Italy compensates energy-intensive companies for the carbon cost passed into electricity prices. In July 2026 the Commission approved an amendment to the scheme (SA.122463). The total budget rises from €1.5 billion to €3.6 billion and the annual ceiling from €140 million to €600 million. Aid intensity rises from 75% to 80%, for sectors already covered. New sectors at risk of carbon leakage become eligible. Final payments are due in 2031.
- Total budget (amended)
- €3.6 billion (from €1.5 billion) European Commission, MEX/26/1656, 20 Jul 2026
- Maximum annual budget
- €600 million (from €140 million) European Commission, MEX/26/1656, 20 Jul 2026
- Maximum aid intensity (existing sectors)
- 80% (from 75%) European Commission, MEX/26/1656, 20 Jul 2026
Source: European Commission, MEX/26/1656, 20 Jul 2026
Legal texts: Compensazione costi indiretti (SA.122463)
Grid fee reliefIn forceSince 1 Apr 2026, non-household users pay about €12 to €14/MWh less in the ASOS system charge.What it means: The system-charge line of the bill is lower. Sites on the CSEA energy-intensive list are excluded.
Since 1 Apr 2026, ARERA has applied an ASOS discount of about €12 to €14/MWh for non-household users under DL 21/2026. Users on the CSEA energy-intensive list are excluded.
Decree-law 21/2026, converted with amendments by Law 49/2026, cuts the ASOS charge, the system charge that funds renewables and cogeneration, for non-household users. ARERA has applied the cut since 1 April 2026 through a negative ASOS element worth about €12 to €14 per MWh, depending on voltage. So far it is funded by a temporary 2-point IRAP rise on energy companies, with resources estimated at €469.6 million for 2026, €545.4 million for 2027 and €74.5 million for 2028, and by bringing forward system-charge payments in 2026. Savings from Conto Energia solar owners who accepted a lower premium by 31 May 2026 are also earmarked for it. Public lighting and companies on the CSEA energy-intensive list are excluded. ARERA raised the overall ASOS charge from 1 July 2026.
- IRAP resources earmarked for the ASOS cut, 2026
- €469.6 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
- IRAP resources earmarked for the ASOS cut, 2027
- €545.4 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
- IRAP resources earmarked for the ASOS cut, 2028
- €74.5 million (estimate) DL 21/2026, art. 3(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
- Deadline for PV owners to opt into a reduced premium
- 31 May 2026 DL 21/2026, art. 2(3), Gazzetta Ufficiale n. 42, 20 Feb 2026
Source: ARERA deliberation 98/2026/R/com, 30 Mar 2026
Legal texts: DL 21/2026 (decreto bollette) · ARERA deliberation 98/2026/R/com
Storage rulesIn forceSince 2022, energy drawn to charge storage and later fed back can be netted, so grid tariffs and system charges apply only to energy consumed.
Since 1 January 2022, a producer can ask for energy drawn from the grid to charge storage, and later fed back, to be treated as negative injection. Transmission and distribution tariffs and system charges then apply only to energy actually consumed. The request needs a single-line diagram and an independent certified rating. If charging power exceeds 110% of the declared value in a month, normal consumer charges apply through a penalty.
- Regime applies from
- 1 Jan 2022 ARERA Delibera 109/2021/R/eel, point 1, 16 Mar 2021
- Penalty threshold for charging power
- 110% of declared power in a month ARERA Delibera 109/2021/R/eel, point 2, 16 Mar 2021
Source: ARERA, Delibera 109/2021/R/eel
Legal texts: ARERA 109/2021/R/eel
Capacity mechanismIn forceTerna capacity market. The first MACSE storage auction awarded 10 GWh in Sep 2025.
Terna runs a capacity market and, separately, MACSE, a scheme that procures new storage under long-term contracts. The first MACSE auction on 30 September 2025 procured 10 GWh in southern Italy and the islands, all of the demand. Bids exceeded demand more than four times. The weighted average price was €12,959 per MWh-year, against a reserve premium of €37,000. The lithium-ion plants are due to start operating in 2028.
- Storage procured, first MACSE auction
- 10 GWh Terna press release, 1 Oct 2025
- Weighted average clearing price
- €12,959/MWh-year Terna press release, 1 Oct 2025
- Reserve premium
- €37,000/MWh-year Terna press release, 1 Oct 2025
Source: Terna via Teleborsa, 1 Oct 2025
Legal texts: Capacity market and MACSE (Terna)
Next dated changeDated21 Dec 2026: Terna holds the main capacity market auction for 2028 delivery.
The rules for the capacity market auction with 2028 delivery were approved by ministerial decree on 6 August 2026, with technical provisions approved on 16 October 2026. Terna has scheduled the main auction for 21 December 2026 at 10:00. Requests to take part could be sent from 20 October to 3 November 2026. The 16 October decree also approved revised de-rating factors for new battery storage, which the ministry had asked Terna to review.
- Capacity market main auction, delivery 2028
- 21 Dec 2026 Terna, notice 'Asta Madre del Mercato della Capacità con periodo di consegna 2028', 19 Oct 2026
- Participation request window
- 20 Oct to 3 Nov 2026 Terna, notice 'Asta Madre del Mercato della Capacità con periodo di consegna 2028', 19 Oct 2026
Source: Terna, 19 Oct 2026
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
Netherlands
The Netherlands plans a €150m price-relief scheme for 2027 and a first capacity auction for 2028, but no grid fee relief.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Net electricity consumption (CBS): CBS StatLine 84575NED, Elektriciteitsbalans; aanbod en verbruik, 30 Oct 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)PlannedThe Dutch cabinet intends to open a €150m CISAF price-relief scheme in 2027.What it means: Dutch sites have no power-price relief yet. The scheme still has to be designed and approved, and half of any aid must be reinvested.
The cabinet intends to open a €150m CISAF price-relief scheme in 2027 (letter to parliament, 3 Nov 2026). Not yet designed or approved.
On 3 November 2026 the cabinet told parliament that it intends to open a €150 million scheme under CISAF section 4.5 in 2027, using the extra room the temporary METSAF framework allows. CISAF requires beneficiaries to invest at least half of the aid in decarbonisation, such as energy efficiency, electrification or flexibility. The scheme is not yet designed or approved. Dutch support for industrial electricity costs currently runs through compensation for indirect carbon costs, the IKC-ETS scheme.
- Planned budget
- €150m, scheme to open in 2027 Kamerbrief Elektriciteitskosten industrie, Tweede Kamer 2026D55256, 3 Nov 2026
Source: Kamerbrief Elektriciteitskosten industrie, 3 Nov 2026
Legal texts: Kamerbrief Elektriciteitskosten industrie (3 Nov 2026)
CO₂ cost compensationIn forceIKC-ETS refunds part of the CO₂ cost built into power prices. The 2026 round had €318m for 2025 costs.What it means: The 2026 round closed on 30 Sep 2026; sites that missed it wait for the next round.
IKC-ETS. The 2026 round (2025 costs, €318m) closed on 30 Sep 2026.
The IKC-ETS scheme refunds part of the carbon cost in power prices. The 2026 round covered costs incurred in 2025, with a budget of €318.2 million. Applications ran from 3 August to 30 September 2026. Aid is 80% of indirect costs for long-listed sectors and 75% for newly added ones. Large companies need an energy audit and must invest at least half the subsidy in carbon reduction. Payment awaits Commission approval.
- Budget ceiling, 2026 round (2025 costs)
- €318,239,000 Staatscourant 2026, nr. 24870, 15 Jul 2026
- Application window
- 3 Aug to 30 Sep 2026 Staatscourant 2026, nr. 24870, 15 Jul 2026
- Aid intensity
- 80% (existing sectors); 75% (newly added sectors) Staatscourant 2026, nr. 24870, 15 Jul 2026
Source: Staatscourant 2026, nr. 24870
Legal texts: IKC-ETS (RVO)
Grid fee reliefNoneThe volume-correction rebate ended in 2024, and no grid-fee relief replaces it.What it means: TenneT proposes 2027 high-voltage tariffs 20% higher on average, with no rebate to offset the rise. ACM decides in November.
The volume-correction rebate ended in 2024. TenneT proposes 2027 high-voltage tariffs 20% higher on average and extra-high-voltage tariffs 6% lower; ACM decides in Nov 2026.
The Netherlands has no grid-fee discount for large consumers. ACM ended the volume-correction scheme, a transport-tariff rebate for users with high, steady consumption, from 2024. It found these users did not cause lower grid costs. ACM's first forecast is that large companies connected to TenneT's high-voltage grid will pay about 20% more in 2027. TenneT's proposal shows high-voltage tariffs up 20% on average and extra-high-voltage tariffs down 6%.
- Expected 2027 change for large users on TenneT's high-voltage grid
- about +20% ACM, first forecast of 2027 tariffs, 14 Sep 2026
- TenneT proposal, average 2027 change: HS / EHS
- +20% / -6% TenneT tariff proposal 2027 (published by ACM), 29 Sep 2026
- Volume-correction rebate ended
- from 2024 ACM, 'in 2024 geen volumekorting meer voor grootverbruikers', 24 May 2023
Source: ACM, 7 Oct 2026
Storage rulesIn forceNon-firm grid contracts with a tariff discount, offered in congested areas since Feb 2025. No storage exemption.
In congested areas, grid operators must offer non-firm transport contracts. These give a discount on the transport tariff in exchange for using the connection only when capacity is available. Operators could offer them from 1 February 2024 and have had to since 1 February 2025. ACM names battery storage among suitable users. We found no general exemption from grid fees for stored energy in the Netherlands.
- Non-firm contracts mandatory in congestion areas from
- 1 Feb 2025 ACM, 31 Jan 2024, 31 Jan 2024
Source: ACM, 31 Jan 2024
Legal texts: Non-firm transport contracts (ACM)
Capacity mechanismPlannedMarket-wide capacity market chosen in Jun 2026. First auction targeted for 2028, subject to state-aid approval.
On 19 June 2026 the cabinet chose a market-wide capacity mechanism to protect against shortages and price spikes. TenneT's monitoring shows the Dutch standard of at most 4 hours of expected shortage a year will be exceeded in all scenarios in 2030. TenneT would run the auctions, with the first targeted for 2028 for supply in 2029 to 2030. Batteries and demand response can take part. The timeline depends on Commission approval.
- First auction targeted
- 2028 Rijksoverheid, 19 Jun 2026, 19 Jun 2026
- Supply period targeted
- 2029 to 2030 Rijksoverheid, 19 Jun 2026, 19 Jun 2026
Source: Rijksoverheid, 19 Jun 2026
Legal texts: Capaciteitsmarkt (planned)
Next dated changeDatedNov 2026: ACM decides on the 2027 tariff proposals of TenneT and the regional grid operators.
ACM is assessing the grid operators' tariff proposals for 2027 and says it will decide on them in November 2026. TenneT's proposal raises average high-voltage transport tariffs by 20% and lowers extra-high-voltage tariffs by 6%. ACM's earlier forecast put the increase for large companies on TenneT's high-voltage grid at about 20%. The final tariffs will show whether ACM adopts TenneT's proposal.
- ACM decision on 2027 tariffs
- November 2026 ACM, 'ACM publiceert tariefvoorstellen netbeheerders 2027', 7 Oct 2026
Source: ACM, 7 Oct 2026
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
Poland
Poland's PLN 4.8bn price-relief bill for 2027 to 2030 is in parliament, and its capacity market has run since 2018.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity demand (PSE): PSE, Raporty za rok 2025 (Raport 2025 KSE), as published (no date on page). Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)DraftThe act would fund PLN 4.8bn of price relief for 2027 to 2030. Parliament passed it on 5 Nov 2026, and it awaits the President's signature.What it means: Aid applied for in 2027 would be based on 2026 consumption, once the act is signed and the Commission approves the scheme.
Act on support for energy-intensive companies, PLN 4.8bn for 2027 to 2030. Passed by parliament on 5 Nov 2026 and with the President since 6 Nov; not yet law.
Poland's act on support for energy-intensive companies implements CISAF section 4.5. It caps support at 50% of the reference price and at a level that keeps the price paid at or above €50 per MWh. Firms must invest at least half the aid in flexibility, electrification or renewables within 48 months. State spending is capped at PLN 4.8 billion over 2027 to 2030. Aid is based on the calendar year before the application, so applications in 2027 would cover 2026 consumption. The act would take effect on 1 January 2027.
- Budget ceiling 2027 to 2030
- PLN 4.8 billion (800m, 1,600m, 1,600m, 800m) Act of 22 Oct 2026 as passed by the Sejm, art. 33(1), 22 Oct 2026
- Maximum support
- 50% of the reference price; price after support not below €50/MWh Act of 22 Oct 2026 as passed by the Sejm, art. 3(4), 22 Oct 2026
- Planned entry into force
- 1 Jan 2027 Act of 22 Oct 2026 as passed by the Sejm, art. 35, 22 Oct 2026
- Qualifying period
- The calendar year before the application (2026 for applications in 2027) Act of 22 Oct 2026 as passed by the Sejm, art. 2(4), 22 Oct 2026
Source: Sejm, process 3159
Legal texts: Sejm, process 3159
CO₂ cost compensationIn forcePoland refunds part of the CO₂ cost built into power prices under the Act of 19 Jul 2019, run by URE.What it means: Applications for the previous year's costs are due by 31 March each year.
Compensation under the Act of 19 Jul 2019, run by URE. Applications are due by 31 Mar for the previous year.
Poland compensates energy-intensive companies for carbon costs passed into electricity prices under the Act of 19 July 2019. The President of URE, the energy regulator, decides on each application. Applications for a year are due by 31 March of the following year, and URE decides by 31 October. Aid intensity is 0.75 in the calculation formulas. The yearly pot equals set ETS auction revenues, cut pro rata if claims exceed it.
- Application deadline
- 31 Mar of the following year Dz.U. 2026 poz. 807, art. 10(2), 29 May 2026
- URE decision deadline
- 31 Oct Dz.U. 2026 poz. 807, art. 11(1), 29 May 2026
- Aid intensity in formulas
- 0.75 Dz.U. 2026 poz. 807, art. 7, 29 May 2026
Source: Dz.U. 2026 poz. 807
Legal texts: Rekompensaty (Act of 19 Jul 2019)
Grid fee reliefIn forceRegistered industrial consumers pay reduced renewable and CHP charges.What it means: Sites must file a declaration by 15 Nov to claim the reduction.
Registered industrial consumers pay reduced renewable and CHP charges. Declarations are due by 15 Nov.
Registered industrial consumers pay the renewable (OZE) and cogeneration charges on only 15% or 25% of the electricity they draw from the grid. To qualify, a firm's main activity must fall under listed PKD codes and its electro-intensity must be at least 3%. Firms file a declaration with an auditor's opinion with URE. For rights in 2026 the deadline was 15 November 2025. Missing it removes the relief for that year.
- Charge basis for registered industrial consumers
- 15% or 25% of electricity drawn and consumed URE, Informacja Prezesa URE nr 59/2025, 6 Nov 2025
- Minimum electro-intensity
- 3% URE, Informacja Prezesa URE nr 59/2025, 6 Nov 2025
- Declaration deadline for 2026 rights
- 15 Nov 2025 URE, Informacja Prezesa URE nr 59/2025, 6 Nov 2025
Source: Enerad, 2025 (secondary)
Storage rulesIn forceNetwork fees on storage are charged on net energy only, including batteries inside a customer's installation with their own meter.
Network charges on energy drawn by a storage facility apply only to the difference between energy taken from and returned to the grid in each billing period. This also covers storage that is part of a final customer's installation, provided it has its own meter recording energy in and out. The contracted capacity used for billing is reduced in proportion to the share of energy the storage returns to the grid.
Source: Energy Law, art. 45 (Dz.U. 2026 poz. 43)
Legal texts: Prawo energetyczne, art. 45
Capacity mechanismIn forceCapacity market since 2018. The delivery-year 2030 auction cleared at PLN 465.02/kW-year.
Poland runs a capacity market under the Capacity Market Act of 8 December 2017, with PSE as operator. The main auction for delivery year 2030 took place on 11 December 2025 and ended in the second round at PLN 465.02 per kW-year for Polish units. It awarded 6,887.639 MW to 198 winning offers. Demand-response units and battery projects were among the winners. Including earlier multi-year contracts, obligations for 2030 total 21,785.155 MW.
- Clearing price, delivery year 2030
- PLN 465.02/kW-year URE, Informacja Prezesa URE nr 1/2026, 2 Jan 2026
- Capacity obligations awarded in the auction
- 6,887.639 MW URE, Informacja Prezesa URE nr 1/2026, 2 Jan 2026
- Auction date
- 11 Dec 2025 URE, Informacja Prezesa URE nr 1/2026, 2 Jan 2026
Source: URE, Informacja 1/2026
Legal texts: Rynek mocy (URE)
Next dated changeDatedWith the President since 6 Nov 2026, who has 21 days to sign or veto the act. Planned entry into force 1 Jan 2027; no aid before Commission approval under CISAF.
The Sejm passed the act on support for energy-intensive companies on 22 October 2026. The Senate adopted 13 amendments on 27 October, and the Sejm accepted them on 5 November. The act went to the President on 6 November; he has 21 days to sign or veto it. The act would take effect on 1 January 2027. Support also needs Commission approval under CISAF and a government aid programme, with applications run by the state bank BGK.
- Sejm vote (third reading)
- 22 Oct 2026 (230 for, 64 against, 145 abstaining) Sejm API, process 3159, 22 Oct 2026
- Senate position (amendments)
- 27 Oct 2026 Sejm API, process 3159, 27 Oct 2026
- Senate amendments accepted; sent to the President
- 5 Nov 2026; 6 Nov 2026 Sejm API, process 3159, 6 Nov 2026
- Planned entry into force
- 1 Jan 2027 Act of 22 Oct 2026, art. 35, 22 Oct 2026
Source: Sejm, process 3159
Checked 31 Oct 2026. Not legal, tax or investment advice.
Country profile
Slovenia
Slovenia's €90m price relief runs from 2026 to 2028, and a separate decree compensates CO₂ costs for 2025 to 2027.
Key figures
Sources: Industrial electricity price: Eurostat, nrg_pc_205, updated 19 Oct 2026, accessed 31 Oct 2026. Day-ahead price, 2025 average: European Commission, Quarterly Report on European Electricity Markets Q4 2025. Renewables share, 2025: BNetzA, REE, RTE, CBS, Agencija za energijo, Ember (2026 releases). Negative-price hours, 2025: BNetzA (5 Jan 2026), RTE (25 Feb 2026), TenneT (30 Apr 2026), GME annual report 2025, Agencija za energijo (30 Jun 2026). Electricity consumption (Agencija za energijo): Agencija za energijo, Poročilo o stanju na področju energetike v Sloveniji v letu 2025, table 5, 30 Jun 2026. Network costs, 20 to 70 GWh users (Eurostat): Eurostat, nrg_pc_205_c, 16 Oct 2026.
Policies
Price relief (CISAF 4.5)In forceSlovenia's ZSKREP relief pays energy-intensive firms part of their power costs for 2026 to 2028, with €90m of funding.What it means: An eligible site gets relief on up to half of its consumption, but must reinvest half of the aid. Both 2026 advances are due by 30 Nov 2026.
Relief under ZSKREP (SA.120965), €90m for 2026 to 2028, paid by Borzen. Requests for 2026 exceed the €30m budget, and both advances are due by 30 Nov 2026.
Slovenia's ZSKREP act implements CISAF section 4.5, and the Commission approved the scheme on 16 April 2026 (SA.120965) with an indicative budget of €90 million for 2026 to 2028. Eligible firms are in CEEAG Annex 1 sectors, have electricity costs above 5% of gross value added over three years, use at least 15 GWh a year and run ISO 50001 or energy audits. Aid covers at most half of a firm's consumption at up to half the reference price, without taking the price below €50/MWh, within a maximum aid per MWh that the government sets each year. Borzen, the market operator, decides on applications, pays two advances and settles against actual consumption by 30 April of the following year. At least half of the aid must go into new investment in renewables, storage, demand flexibility, efficiency, waste-heat recovery, electrolysers or electrification, operating within 48 months. Requests for 2026 exceed the €30 million budget, so any pro rata cut to the €30/MWh cap follows Borzen's review of all applications, and both advances are due by 30 November 2026.
- Indicative budget 2026 to 2028
- €90 million European Commission, C(2026) 2564, SA.120965, recital 31, 16 Apr 2026
- Budget and maximum aid for 2026
- €30 million; €30.00/MWh Vlada RS, sklep 00704-145/2026, Uradni list RS 627/2026, 15 May 2026
- Reference price for 2026
- €102.24/MWh (2025 average of the EEX-PXE Slovenian Power Base Year Future) Borzen, JP EI 2026, section 6.3, 29 May 2026
- National eligibility tests
- Electricity costs above 5% of gross value added; at least 15 GWh a year; ISO 50001 or energy audits ZSKREP, art. 2 and 3, Uradni list RS 12/2026, 17 Feb 2026
- Both 2026 advances paid by
- 30 Nov 2026 Borzen, press release, 16 Sep 2026, 16 Sep 2026
- Budget and maximum aid for 2027 set by
- 31 Jan 2027 ZSKREP, art. 11(1), Uradni list RS 12/2026, 17 Feb 2026
Source: Borzen, 16 Sep 2026
Legal texts: Borzen, spodbude za elektrointenzivna podjetja · ZSKREP (PISRS) · Akt o prispevkih OVE in SPTE (Agencija za energijo) · Pogoji za PSI (ELES)
CO₂ cost compensationIn forceSlovenia refunds part of the CO₂ cost built into power prices under a decree for 2025 to 2027.What it means: Claims for 2026 costs are due between 31 Mar and 30 Apr 2027. For 2025 costs the aid intensity is 0.728, against a maximum of 0.75.
Compensation for 2025 to 2027 under a March 2026 decree, run by the environment ministry. Claims for 2026 costs are due between 31 Mar and 30 Apr 2027.
Slovenia compensates indirect carbon costs in electricity prices under a government decree for 2025 to 2027, adopted on 12 March 2026 under State aid scheme SA.120932. A firm first applies to the ministry responsible for climate for a right to compensation, by 30 September 2027 at the latest, with a plan for spending it. It then claims the amount for each past year between 31 March and 30 April; claims for 2025 costs were due by 31 July 2026. The minister sets the aid intensity each year from the budget and the claims received, up to 0.75. Beneficiaries must cover at least 30% of their consumption from low-carbon sources and spend all the compensation on renewables, efficiency or emission cuts within two years of the last payment.
- Amount for 2025 costs
- €26,000,000 Ministrstvo za okolje in prostor, Sklep o višini zneska za kritje posrednih stroškov, 2025, 14 Aug 2026
- Aid intensity for 2025 costs
- 0.728 (maximum 0.75) Ministrstvo za okolje in prostor, Sklep o maksimalni intenzivnosti pomoči za leto 2025, 7 Oct 2026
- Claims for a year's costs
- 31 Mar to 30 Apr of the following year Uredba, Uradni list RS 61/2026, art. 8(1), 16 Mar 2026
- Deadline to apply for the right to compensation
- 30 Sep 2027 Uredba, Uradni list RS 61/2026, art. 4(2), 16 Mar 2026
- Low-carbon supply condition
- At least 30% of the site's consumption Uredba, Uradni list RS 61/2026, art. 6(1), 16 Mar 2026
Source: Uradni list RS 61/2026, art. 8
Legal texts: Nadomestilo za posredne stroške emisij (gov.si) · Uredba 2025 in 2027 (PISRS)
Grid fee reliefIn forceEnergy-intensive users registered with Borzen's Centre for Support pay 30% of the standard renewables and CHP contribution.What it means: A draft decree would charge them €0.00185/kWh from 1 Jan 2027, half the general rate of €0.0037/kWh.
Energy-intensive users registered with Borzen's Centre for Support pay 30% of the standard renewables and CHP contribution. A draft decree would charge them €0.00185/kWh, half the general rate, from 1 Jan 2027.
Final customers pay a monthly contribution per kW of billing power to fund renewable and CHP support, at rates the Energy Agency sets for each user group. Customers in listed energy-intensive sectors pay 30% of the standard rate if their electro-intensity exceeds 5%, they use more than 1 GWh a year at the metering point and they are registered with Borzen's Centre for Support, among other conditions. On a medium-voltage feeder the standard rate is €3.44078 and the reduced rate €1.03223 per kW a month. A draft decree, open for comment until 13 November 2026, would replace this from 1 January 2027 with €0.0037 per kWh consumed, and €0.00185 per kWh for eligible electro-intensive companies.
- Contribution on a medium-voltage feeder, standard / reduced
- €3.44078 / €1.03223 per kW of billing power a month Agencija za energijo, Akt o prispevkih, art. 3 and 4, Uradni list RS 83/2024, 27 Sep 2024
- Contribution on high voltage, standard / reduced
- €2.97160 / €0.89148 per kW of billing power a month Agencija za energijo, Akt o prispevkih, art. 3 and 4, Uradni list RS 83/2024, 27 Sep 2024
- Thresholds for the reduced rate
- Electro-intensity above 5%; above 1 GWh a year at the metering point (three-year average) Uredba o načinu določanja in obračunavanja prispevkov, art. 6(3), Uradni list RS 184/2021, 26 Nov 2021
- Draft rate from 1 Jan 2027, general / electro-intensive
- €0.0037 / €0.00185 per kWh Ministrstvo za infrastrukturo in energetiko, 3 Nov 2026, 3 Nov 2026
Source: Agencija za energijo, Uradni list RS 83/2024
Legal texts: Predlog uredbe o prispevkih za OVE (gov.si)
Storage rulesIn forceA site that owns its battery pays no network charges or other costs on stored energy it exports or uses for grid flexibility services. A third party may install and run it.
Under the Electricity Supply Act (ZOEE), an active customer that owns a storage facility pays no network charges or other costs on stored energy it feeds back into the grid, and none on energy it stores or releases while providing flexibility services to system operators. Active customers include final customers that store self-generated electricity or take part in flexibility schemes, provided this is not their main business. A site may hand installation, operation, data handling and maintenance to a third party, which does not itself become an active customer. Separately, batteries connected directly to the high- or medium-voltage grid that only store and re-inject energy pay no network charges, including the connection-capacity charge, for three years from their use permit, if their connection consent is issued within three years of 12 July 2025.
- Storage owned by an active customer
- No network charges or other costs on stored energy fed back, or stored and released for flexibility services ZOEE, art. 23(7), Uradni list RS 172/2021, 29 Oct 2021
- Third-party role
- Installation, operation, data handling and maintenance may be transferred to a third party ZOEE, art. 23(3), Uradni list RS 172/2021, 29 Oct 2021
- Batteries connected directly at high or medium voltage
- No transmission, distribution or connection-capacity network charges for 3 years from the use permit ZOEE-A, art. 29 (ZOEE art. 109(6)), Uradni list RS 47/2025, 27 Jun 2025
- Connection consent window for that exemption
- Within 3 years of 12 Jul 2025 ZOEE-A, art. 46 and 52, Uradni list RS 47/2025, 27 Jun 2025
Source: ZOEE, art. 23 (Uradni list RS 172/2021)
Legal texts: ZOEE (PISRS)
Capacity mechanismNoneNo capacity mechanism. ACER's map of capacity mechanisms in the EU in 2025 shows none in Slovenia.
Slovenia has no capacity mechanism, and ACER's 2025 map of capacity mechanisms in the EU shows none in Slovenia. The Electricity Supply Act lets the ministry include a capacity mechanism in a plan to fix adequacy problems, subject to State aid rules and the Commission's opinion. A 2025 amendment added a legal basis for a non-fossil flexibility support scheme: the government sets an indicative target from the Energy Agency's flexibility needs assessment and may adopt a support programme, which Borzen's Centre for Support would run through annual calls funded by a levy on network bills. The Energy Agency published the first assessment, for 2030 and 2035, on 21 August 2026. We found no adopted programme.
- Capacity mechanisms in the EU, 2025
- None in Slovenia ACER, Security of EU electricity supply 2025, p. 12, 20 Nov 2025
- Legal basis for a capacity mechanism
- ZOEE art. 39 (optional, via an adequacy implementation plan) ZOEE, art. 39, Uradni list RS 172/2021, 29 Oct 2021
- Legal basis for a non-fossil flexibility support scheme
- ZOEE art. 44.a to 44.e, added in 2025 ZOEE-A, art. 23, Uradni list RS 47/2025, 27 Jun 2025
- Flexibility needs assessment published
- 21 Aug 2026 (target years 2030 and 2035) Agencija za energijo, 21 Aug 2026, 21 Aug 2026
Source: ACER, Security of EU electricity supply 2025, p. 12
Legal texts: ACER, Security of EU electricity supply 2025
Next dated changeDated1 Jan 2027: the minimum billed capacity in time block 1 for sites above 43 kW rises from 15% to 20% of connection capacity. A draft decree would also charge the renewables contribution per kWh.
From 1 January 2027, sites with a connection above 43 kW are billed for at least 20% of their connection capacity in time block 1, the highest-priced block, instead of 15%; the floor rises to 25% from 2028. On the same date, a draft decree would replace the renewables and CHP contribution with a charge per kWh consumed. By 31 January 2027 the government sets the 2027 budget and maximum aid per MWh for the ZSKREP relief, and Borzen opens the 2027 call within ten working days. Recipients of 2026 relief report to Borzen by 1 April 2027, and Borzen settles 2026 aid by 30 April 2027.
- Minimum billed capacity in time block 1, sites above 43 kW
- 20% of connection capacity in 2027; 25% from 2028 (15%, at least 8.6 kW, before) Agencija za energijo, Uradni list RS 753/2026, 26 May 2026
- Draft renewables contribution from 1 Jan 2027
- €0.0037/kWh; €0.00185/kWh for eligible electro-intensive companies Ministrstvo za infrastrukturo in energetiko, 3 Nov 2026, 3 Nov 2026
- 2027 relief budget and maximum aid set by
- 31 Jan 2027 ZSKREP, art. 11(1), Uradni list RS 12/2026, 17 Feb 2026
- Settlement of 2026 relief
- by 30 Apr 2027 ZSKREP, art. 6(5), Uradni list RS 12/2026, 17 Feb 2026
Checked 11 Nov 2026. Not legal, tax or investment advice.
Country profile ·
In preparation
Nine market profiles are available. Tracked dates for all markets are on Upcoming dates.